How Long Does LADBS Permitting Take in Los Angeles in 2026?
The Los Angeles Department of Building and Safety (LADBS) is one of the busiest permitting authorities in the United States. Understanding realistic permit timelines — and how to move through the process faster — is essential for any construction project in the city.
LADBS Permit Timeline by Project Type (2026)
- Simple ADU (pre-approved plan): 4–8 weeks
- Custom ADU (architect-designed): 10–20 weeks
- Home addition under 500 sq ft: 8–14 weeks
- Second-story addition: 12–24 weeks
- New single-family home: 16–30 weeks
- Commercial tenant improvement: 8–16 weeks
- New multifamily construction (5+ units): 20–52 weeks
- High-rise or complex commercial: 12–24+ months
The Plan Check Process: What Actually Takes So Long
Most of the time in an LADBS permit is spent in plan check — city engineers reviewing your construction documents for code compliance.
First Submittal
You submit architectural plans, structural calculations, Title 24 energy documentation, and other required materials. Wait time for first plan check response: 3–10 weeks depending on project type and current backlog.
Correction Notices
Almost every project receives correction notices. Simple projects may receive 5–15 corrections; complex projects can receive 50+. Your designer must respond to each, revise the plans, and resubmit.
Second and Third Submittals
Projects sometimes go through 3–4 rounds of plan check before receiving approval. Each round adds 2–6 weeks.
How to Speed Up the LADBS Process
1. Submit Complete, Code-Compliant Plans First
The single most effective accelerator. Incomplete submittals are returned immediately, wasting weeks. Work with an architect and structural engineer who know LADBS requirements cold.
2. Use Pre-Approved Plans When Available
LADBS and California have pre-approved ADU plan sets that permit over-the-counter with minimal review — sometimes 3–4 months faster than custom design.
3. Request Expedited Plan Check
LADBS offers expedited review for an additional fee. For time-sensitive projects, paying for expedited review can cut standard timelines by 30–50%.
4. Hire a Permit Expeditor
Permit expeditors navigate LADBS on your behalf — tracking status, responding quickly to corrections, and ensuring nothing falls through the cracks. A good expeditor can save months on complex projects.
5. Respond to Corrections Immediately
The clock stops when LADBS sends corrections and doesn't restart until you resubmit. Responding within days rather than weeks can shave 4–8 weeks off your total timeline across multiple correction rounds.